City Island II Progress
· The construction is now up to full height.
· The dismantling of crane 1, the shorter of the two, will provisionally be dismantled on the 22nd of April. This will entail some disruption as the road will be closed, and we will have to drive in to the development the opposite way to normal. They are just waiting on the council to agree, but they don’t see this as a problem. The council will send out a letter to all residents.
· The second crane, the taller of the two, will be dismantled sometime in August.
· The external envelope is now getting closed in so the mast climbers will be dropped in sequence moving around the building (from the canal side).
· Construction, at the time of writing, is still on schedule to finish in January.